Indonesia Reviews Water Supply for BDx's 640MW AI Campus After Construction Halt
West Java authorities are reviewing water requirements for BDx Data Centers' planned 640MW AI campus near Jatiluhur Reservoir after construction was suspended in September over missing environmental (AMDAL) and building (PBG) approvals. IESR estimates full-scale demand at about 384 liters per second (33,000 cubic meters daily), while an October 5 review cited 27 liters per second. BDx has secured 845 MVA of grid capacity from PLN and targets early 2027 for its first phase.
- Construction of BDx's 640MW campus halted over missing AMDAL and PBG permits
- IESR estimates full water demand at 384 liters per second, or 33,000 m³ daily
- BDx secured 845 MVA from PLN; first phase covers 120MW of IT capacity
- First contracted phase is targeted for early 2027, pending approvals