Crusoe files for $4.8bn data center campus in Jayton, Texas
Crusoe has filed two applications with the Texas Department of Licensing and Regulation for data center buildings in Jayton, Kent County. Each building will span 759,260 sq ft (70,540 sqm), with total investment of $4.8bn; construction starts in late January 2027 and the buildings are due live in May and July 2029.
- Two buildings of 759,260 sq ft (70,540 sqm) each
- Total site investment of $4.8bn
- Construction to begin in late January 2027
- Buildings expected live in May and July 2029