Oracle sends force majeure notice to Blue Owl over 2.45GW Project Jupiter data center
Oracle has sent Blue Owl a force majeure notice to delay payments on its 2.45GW Project Jupiter data center in New Mexico if the facility fails to launch in 2028. The move aims to shield Oracle from racking up expenses on the construction.
- Oracle sent Blue Owl a force majeure notice for Project Jupiter
- The New Mexico data center is planned at 2.45GW
- Payments would be delayed if it misses a 2028 launch
- Oracle aims to shield itself from construction expenses