Clayco and Kiewit have topped out the first 855,000-square-foot building of the Project Jupiter data center campus in Doña Ana County, New Mexico. Stack and Oracle are developing the 1,400-acre site to host AI infrastructure for OpenAI, with full build-out potentially reaching 2.5 GW.
- First phase of Project Jupiter spans 855,000 sq ft (79,432 sqm)
- The 1,400-acre campus will include four buildings, gas power plants and a desalination plant
- Full build-out could reach up to 2.5 GW
- Cooling will use non-potable well water, not public drinking water