Crusoe drops $1.25B plan to use Boom turbines at AI data centers
Crusoe has ended its partnership with Boom Supersonic, scrapping plans to spend $1.25 billion on 29 of Boom's 42-megawatt Superpower gas turbines for AI data centers, including its Abilene, Texas campus. Boom says it will deliver about 250MW of Superpower turbines to other sites next year and targets 1GW in 2028.
- Crusoe was to buy 29 Superpower turbines at 42MW each for $1.25B
- Deliveries were slated to start in 2027, but the deal fell apart
- Boom will ship ~250MW to other customers in 2027, targeting 1GW in 2028
- Crusoe cited shifting power needs across its data center sites