UK's 'largest supercomputer' delayed over power supply problems
A datacentre in Loughton, Essex, billed as the UK's largest AI supercomputer, will miss its 2027 launch after grid operator UK Power Networks told developer Nscale sufficient power won't be available until the early-to-mid 2030s. The site needs up to 90MW, equivalent to about 315,000 homes.
- Loughton datacentre launch slips from 2027 to the early-to-mid 2030s
- UKPN says the grid cannot supply enough power until the 2030s
- The site seeks up to 90MW, equal to about 315,000 homes
- Nscale is exploring on-site generation and faster grid connection