AI Data Centers Are Burning Through Grid Equipment and Squeezing Out Industry

AI training loads degrade transformers and substations two to three times faster than normal, while lead times for high-voltage transformers stretched from 50 weeks in 2021 to 140–160 weeks in 2026. One data center buildout blocked a copper miner's $800 million equipment order.

AI Data Centers Are Burning Through Grid Equipment and Squeezing Out Industry
#Google#Microsoft#Amazon#Meta