California utility PG&E reported its data center pipeline grew marginally to 12.87GW from 12.71GW in July during its Q3 earnings call. Construction-stage capacity rose to 240MW from 140MW in June, and the utility has brought 174MW online since 2024. PG&E is awaiting a California Public Utilities Commission decision on a 250MW Google data center in San Jose.