Nvidia DSX POD packs 504 GPUs into a container with 14-day deployment
Nvidia unveiled the DSX POD at GTC Berlin, a factory-integrated AI data center in a roughly 28-ton container with seven Vera Rubin NVL72 racks, 504 GPUs and 252 Vera CPUs. Shipping starts in early 2027, and deployment at a prepared site can take as little as 14 days instead of about six months.
- Container holds 7 Vera Rubin NVL72 racks: 504 GPUs, 252 Vera CPUs
- Module weighs about 28 metric tons and needs special logistics and cranes
- The 14-day figure applies only where power and cooling already exist
- Shipping is targeted for early 2027