Israel's Electrical Authority has limited new data centers to 200MW to stop speculative projects from clogging the grid connection queue. Developers must post NIS 2 million ($643,300) guarantees per megawatt requested and provide backup mechanisms for disconnection during peak demand.
- 200MW cap per project aims to filter speculative grid connection requests
- Guarantee set at NIS 2 million ($643,300) per MW of requested capacity
- An extra 1GW allocated, bringing sector total to more than 3GW
- NOGA reported roughly 27GW of projects seeking grid connection