FERC approves PJM's request to create data center database
FERC has approved PJM Interconnection's request to build a data center database covering location, power providers, in-service dates and backup generation. The regulator rejected PJM's separate proposal to temporarily curtail power to data centers during grid stress, saying it exceeded the RTO's authority.
- FERC approved a data center database across PJM's footprint
- PJM's curtailment plan for data centers during peak demand was rejected
- PJM projects data center demand to triple to 29GW by 2030
- A July voltage disturbance took more than 3GW offline