Power approval set to delay Oracle's Wisconsin AI datacenter

Oracle's Wisconsin AI datacenter may miss its planned 2027 start because the grid connection awaits approval from the Public Service Commission of Wisconsin. Aterio's base case puts partial power in December 2027 and full supply in October 2028.